FY22

FY22 was our first FPC in Alma.

Messaging

Dear Colleagues,

With this being the first fiscal period close done in Alma, we thought it would be useful to outline exactly what work can and cannot be done during the period of fiscal period close.

After the close of business today until we send a message that the fiscal period close process is done, the following work has to be paused:

Electronic resources: creating/deleting/activating portfolios attached to PO lines

Metadata: modifying holdings, location changes

Inventory management: receiving items, location changes in item records

Acquisitions and Finance: creating/modifying/deleting PO lines, creating/modifying/deleting invoices, receiving items

All fulfillment work (checking items in and out, collecting fines, updating users, etc.) can continue uninterrupted.

If in doubt, you may contact me (Mark Zelesky) directly. We will send out a message when work can resume.

We also wanted to provide an update on where funds stand. As of today, June 24th, the Cash Balance of all FY22 funds should be final for the fiscal year. The Cash Balances of FY22 funds become the initial balances of FY23 funds. Encumbrances for one-time purchases on FY22 funds will carry over to FY23, but the total encumbrance for FY23 will not be known until all lines are rolled over. This is scheduled to be completed on June 28th.

Finally, endowment income distributions and general endowment allocations will be in place the week of July 25, 2022. Ordering and payment of invoices will not be delayed until such time.

Please contact me if there are any questions you have.

Thank you on behalf of the year-end closing team,

 Mark 

Mark Zelesky

Library Discovery and Integrated Library System Analyst/Coordinator Princeton University Library

8-2563

Dear Colleagues,

The fiscal period rollover process has concluded. At this time, the following work can resume:

Electronic resources: creating/deleting/activating portfolios attached to PO lines

Metadata: modifying holdings, location changes

Inventory management: receiving items, location changes in item records

Acquisitions: receiving items

PO lines and invoices cannot yet be directly added/modified/deleted. That work can resume on July 1st.

Thank you again for your patience while we performed the first fiscal period close in Alma. With the lessons learned, next year should be even smoother.

Thank you,

Mark Zelesky

Library Discovery and Integrated Library System Analyst/Coordinator Princeton University Library

8-2563

Alma FY 22 Year-End Close Schedule

Alma Fiscal Year 2022 YEAR_END CLOSE SCHEDULE

Alma Fiscal Year 2022 YEAR_END CLOSE SCHEDULE

Data Cleanup & Reconciliation

Audience

May

 

 

Review all Rollover documentation

Acquisitions/Finance/Alma Tech Team

May

 

 

Department review of financial reports, and make adjustments as needed

Selectors

May

 

 

Review encumbrances for appropriateness, make needed adjustments

Selectors/Acquisitions

May

 

 

Review and ensure all expected transfer journals are accounted for are fully approved by month end

Selectors/Finance

May

 

 

Review, substantiate, and submit any purchasing card transactions from all closed statement periods

Acquisitions/Finance

May

 

 

Onboard suppliers for goods or services that are planned to purchase in FY22

Selectors/Finance

May

 

 

Enter Requests for purchases and submit for approval, for FY22 purchase of goods and services

Selectors

May

 

 

Notify Acquisitions Department to close fully executed or unneeded PO’s

Selectors

May

 

 

Perform receipt of goods in Alma when physically received

Selectors/Acquisitions/Inventory Management

TEST ROLLOVER / SANDBOX

 

5/26/2022

Thur

 

Run rollover in sandbox

Alma Tech Team

5/27/2022

Fri

 

Review results

Collection Development/Finance/Acquisitions

5/30/2022

Mon

HOLIDAY - MEMORIAL DAY

HOLIDAY - MEMORIAL DAY

HOLIDAY - MEMORIAL DAY

5/31/2022

Tue

HOLIDAY

HOLIDAY - EXTRA DAY

HOLIDAY

1st CLOSE/ROLLOVER

 

6/15/2022

Wed

4:30 PM

All invoices must be received by Library Finance for FY22

Acquisitions/Selectors

6/15/2022

Wed

4:30 PM

Last day to import EDI invoices

Alma Tech Team

6/16/2022

Thur

4:30 PM

Audit fund balances

Finance

6/16/2022

Thurs

4:30 PM

Last day to load PO lines from any method

All those responsible for PO line creation

6/17/2022

Fri

HOLIDAY - JUNETEENTH

HOLIDAY

HOLIDAY

6/20/2022

Mon

HOLIDAY

HOLIDAY - EXTRA DAY

HOLIDAY

6/21/2022

Tue

4:30 PM

Delete 'In Review' invoices if necessary

Finance

6/27/2022

Mon

9:00 AM

Begin the rollover process

Alma Tech Team

6/28/2022

Tue

All day

Troubleshoot/test

ALL

6/29/2022

Wed

All day

Audit fund balances

Finance/Collection Development/Selectors

6/30/2022

Thur

All day

Fund allocation work for FY23 ledger

Finance/Collection Development/Selectors

END OF FY2022/START OF FY2023

 

7/1/2022

Fri

 

FY23 open for activity

 

7/4/2022

Mon

HOLIDAY ‐ INDEPENDENCE DAY

HOLIDAY ‐ INDEPENDENCE DAY

HOLIDAY ‐ INDEPENDENCE DAY

7/5/2022

Tue

HOLIDAY ‐ EXTRA DAY OFF

HOLIDAY ‐ EXTRA DAY OFF

HOLIDAY ‐ EXTRA DAY OFF

7/7/2022

Thu

12:00 PM

First day invoices can be approved for FY23

 

Fiscal Period Close FY22

The working document was a Google Sheet. This table is here for informational purposes and for future reference.

Task

Task Name

Duration

Start

Finish

Predecessors

Assigned To

Comments

Task

Task Name

Duration

Start

Finish

Predecessors

Assigned To

Comments

1

Review all rollover documentation

7d

05/10/22

05/18/22

 

All

Ex Libris FPC documentation
Ex Libris FPC basic training

2

Department review of financial reports, and make adjustments as needed

16d

05/10/22

05/31/22

 

Library Finance

Marking complete on June 28th since FY22 is closed

3

Review encumbrances for appropriateness, make needed adjustments

16d

05/10/22

05/31/22

 

Selectors

Marking complete on June 28th since FY22 is closed

4

Review and ensure all expected transfer journals are accounted for are fully approved by month end

16d

05/10/22

05/31/22

 

Library Finance

Marking complete on June 28th since FY22 is closed

5

Review, substantiate, and submit any purchasing card transactions from all closed statement periods

19d

05/10/22

06/03/22

 

Selectors

Marking complete on June 28th since FY22 is closed

6

Onboard suppliers for goods or services that are planned to purchase in FY22

16d

05/10/22

05/31/22

 

 

Marking complete on June 28th since FY22 is closed

7

Enter Requests for purchases and submit for approval, for FY22 purchase of goods and services

16d

05/10/22

05/31/22

 

Selectors/Acquisitions

Marking complete on June 28th since FY22 is closed

8

Notify Acquisitions Department to close fully executed or unneeded POs

16d

05/10/22

05/31/22

 

Selectors

Marking complete on June 28th since FY22 is closed

9

Move active PO lines still attached to Voyager ledger to current fund structure

10d

05/19/22

06/01/22

 

 

 

10

Convert one-time orders that are currently Partially Invoiced to Fully Invoiced

4d

05/24/22

05/27/22

 

 

 

11

Perform receipt of goods in Alma when physically received

16d

05/10/22

05/31/22

 

Acquisitions/Holdings Management

 

12

Rollover test 1: one ledger in sandbox

0

05/19/22

05/19/22

 

Alma Tech Team

Science Ledger

13

Rollover test 1: one PO line in sandbox

1d

05/19/22

05/19/22

12

Alma Tech Team

22660-princetondb; also try 1046794-princetondb

14

Rollover test 1: review results

1d

05/20/22

05/20/22

13

Alma Tech Team

 

15

Rollover test 2: all ledgers in sandbox

0

05/26/22

05/26/22

 

Alma Tech Team

Began at 10:39 AM; took 1 minute; for this year, we should roll over each ledger individually to avoid rolling over the ledger (named 'FY22') with the old fund structure; run in Draft, then Activate after evaluating the balances

16

Rollover test 2: all PO lines in sandbox in Report mode

0

05/26/22

05/26/22

15

Alma Tech Team

POL Rollover cannot be undone; began at 11:05 AM and ended at 9:16 PM

17

Rollover test 2: review results

1d

05/26/22

05/26/22

16

Alma Tech/Acq/Finance

199 lines did not roll over due to being on old Voyager funds; we will work to move them to proper funds in prod prior to the prod rollover

18

Rollover test 3: all PO lines in sandbox in Update mode

0

05/27/22

05/27/22

 

Alma Tech Team

Began at 11:31 AM; finished 5/28 at 6:50 AM

19

Rollover test 3: review results

6d

05/27/22

06/03/22

18

Alma Tech/Acq/Finance

 

20

All invoices must be received by Library Finance for FY22 by 4:30 PM

0

06/15/22

06/15/22

 

 

 

21

Last day to import EDI invoices by 4:30 PM

0

06/15/22

06/15/22

 

 

 

22

Disable EDI loading on vendors that are on auto-pilot (EBSCO and Midwest)

1d

06/16/22

06/16/22

 

 

 

23

Last day to approve invoices in ALMA by 4:30 PM

0

06/16/22

06/16/22

 

 

Final export of invoices from Alma is 6/16 at 7 PM

24

Disable voucher feed lib-job script

0

06/17/22

06/17/22

 

Alma Tech Team

 

25

Delete 'In Review' invoices by 4:30 PM

0

06/21/22

06/21/22

 

 

 

26

Convert one-time orders that are currently Partially Invoiced to Fully Invoiced

0

06/21/22

06/21/22

 

 

 

27

Disable loaders for PO lines

8d

06/22/22

07/01/22

 

Alma Tech Team

 

28

Disable PeopleSoft integrations

6d

06/24/22

07/01/22

 

 

 

29

Disable jobs that touch invoices and PO lines

8d

06/22/22

07/01/22

 

Alma Tech Team

PO renewal was not able to be closed, but other jobs were disabled

30

All work on invoices stopped

7d

06/22/22

06/30/22

 

Finance

 

31

All work on PO lines stopped by 4:30 PM

5d

06/21/22

06/27/22

 

Acq/Finance

All work on PO lines was stopped by noon June 22

32

Inactivate FY22 Ledgers, Summary, and Allocated Funds

0

06/22/22

06/22/22

 

 

 

33

Create report of final FY22 budget

1d

06/22/22

06/22/22

27

 

 

34

Reconcile Alma report of final FY22 numbers with Prime

1d

06/22/22

06/22/22

 

 

This review will happen throughout the year, quarterly

35

Rollover test 3: all ledgers in production rolled over in draft

0

06/22/22

06/22/22

34

Alma Tech Team

 

36

Rollover test 3: review ledger rollover and draft budget reports

1d

06/22/22

06/23/22

36

Alma Tech Team

Allocated Balances for FY23 matched all cash balances from FY22, so the final FY22 report for funds can be used for fund allocation work

37

Rollover test 3: roll over all PO lines in Report mode

1d

06/22/22

06/23/22

37

Alma Tech Team

Started at 2:50 PM on 6/22; ended at 6 PM; first attempt resulted in most lines failing due to the FY23 funds being in Draft; running a second time, began at 9 AM on 6/23 and finished at 2 PM on 6/23 for the one-time orders and went from 6 PM on 6/23 to 12:03 AM on 6/24

38

Rollover test 3: review PO line rollover reports

1d

06/23/22

06/24/22

37

Alma Tech Team

No lines had errors

39

All physical receiving stopped at 5 PM

5d

06/24/22

06/30/22

 

Receiving

 

40

All activation/deactivation of portfolios attached to PO lines stopped at 5 pm

5d

06/24/22

06/30/22

 

Electronic Resources

 

41

All work on physical holdings and portfolios attached to orders stopped at 5 PM

5d

06/24/22

06/30/22

 

Electronic Resources/Cataloging/Acq

 

42

Production rollover: delete all FY23 draft ledgers

0

06/27/22

06/27/22

 

Alma Tech Team

 

43

Production rollover: roll over all ledgers in Update mode

0

06/27/22

06/27/22

 

Alma Tech Team

Began at 9:37 AM on 6/27, completed at 9:39 AM

44

Production rollover: run initial budget report

0

06/27/22

06/27/22

42

Alma Tech Team

 

45

Production rollover: roll over all PO lines in Update mode

1d

06/27/22

06/28/22

42

Alma Tech Team

Began at 9:53 AM on 6/27, completed at 8:55 AM on 6/28; PO lines attached to an In Review PO did not roll over (see PO-799006)

46

Production rollover: review PO line rollover reports

1d

06/28/22

06/28/22

44

Alma Tech Team/Acq/Finance/Selectors

No errors

47

Production rollover: create budget report that includes encumbrances

1d

06/28/22

06/28/22

44

 

 

48

Re-enable PeopleSoft integrations and all Acquisitions jobs

0

06/28/22

06/28/22

 

 

 

49

Audit fund balances

3d

06/28/22

06/30/22

46

Alma Tech Team/Acq/Finance

Alma Tech Team looked at the encumbrances left on FY22 and found that lines fully invoiced in FY22 but not yet received have an encumbrance remaining in FY22 until the item is received

50

Fund allocation work for FY23 ledger

13d

06/28/22

07/14/22

46

 

 

51

FY23 open for activity except for invoice approval

0

07/01/22

07/01/22

 

 

 

52

First day invoices can be approved for FY23

0

07/07/22

07/07/22

 

 

 

53

Turn in budget reports to Patty by 4:30 PM

0

07/08/22

07/08/22

 

Selectors

Next year, this will be the middle of May

54

FY 23 Endowment income distributions and general endowment allocations post

0

07/21/22

07/21/22