FY22
FY22 was our first FPC in Alma.
Messaging
Alma FY 22 Year-End Close Schedule
Alma Fiscal Year 2022 YEAR_END CLOSE SCHEDULE | ||||
---|---|---|---|---|
Data Cleanup & Reconciliation | Audience | |||
May |
|
| Review all Rollover documentation | Acquisitions/Finance/Alma Tech Team |
May |
|
| Department review of financial reports, and make adjustments as needed | Selectors |
May |
|
| Review encumbrances for appropriateness, make needed adjustments | Selectors/Acquisitions |
May |
|
| Review and ensure all expected transfer journals are accounted for are fully approved by month end | Selectors/Finance |
May |
|
| Review, substantiate, and submit any purchasing card transactions from all closed statement periods | Acquisitions/Finance |
May |
|
| Onboard suppliers for goods or services that are planned to purchase in FY22 | Selectors/Finance |
May |
|
| Enter Requests for purchases and submit for approval, for FY22 purchase of goods and services | Selectors |
May |
|
| Notify Acquisitions Department to close fully executed or unneeded PO’s | Selectors |
May |
|
| Perform receipt of goods in Alma when physically received | Selectors/Acquisitions/Inventory Management |
TEST ROLLOVER / SANDBOX |
| |||
5/26/2022 | Thur |
| Run rollover in sandbox | Alma Tech Team |
5/27/2022 | Fri |
| Review results | Collection Development/Finance/Acquisitions |
5/30/2022 | Mon | HOLIDAY - MEMORIAL DAY | HOLIDAY - MEMORIAL DAY | HOLIDAY - MEMORIAL DAY |
5/31/2022 | Tue | HOLIDAY | HOLIDAY - EXTRA DAY | HOLIDAY |
1st CLOSE/ROLLOVER |
| |||
6/15/2022 | Wed | 4:30 PM | All invoices must be received by Library Finance for FY22 | Acquisitions/Selectors |
6/15/2022 | Wed | 4:30 PM | Last day to import EDI invoices | Alma Tech Team |
6/16/2022 | Thur | 4:30 PM | Audit fund balances | Finance |
6/16/2022 | Thurs | 4:30 PM | Last day to load PO lines from any method | All those responsible for PO line creation |
6/17/2022 | Fri | HOLIDAY - JUNETEENTH | HOLIDAY | HOLIDAY |
6/20/2022 | Mon | HOLIDAY | HOLIDAY - EXTRA DAY | HOLIDAY |
6/21/2022 | Tue | 4:30 PM | Delete 'In Review' invoices if necessary | Finance |
6/27/2022 | Mon | 9:00 AM | Begin the rollover process | Alma Tech Team |
6/28/2022 | Tue | All day | Troubleshoot/test | ALL |
6/29/2022 | Wed | All day | Audit fund balances | Finance/Collection Development/Selectors |
6/30/2022 | Thur | All day | Fund allocation work for FY23 ledger | Finance/Collection Development/Selectors |
END OF FY2022/START OF FY2023 |
| |||
7/1/2022 | Fri |
| FY23 open for activity |
|
7/4/2022 | Mon | HOLIDAY ‐ INDEPENDENCE DAY | HOLIDAY ‐ INDEPENDENCE DAY | HOLIDAY ‐ INDEPENDENCE DAY |
7/5/2022 | Tue | HOLIDAY ‐ EXTRA DAY OFF | HOLIDAY ‐ EXTRA DAY OFF | HOLIDAY ‐ EXTRA DAY OFF |
7/7/2022 | Thu | 12:00 PM | First day invoices can be approved for FY23 |
|
Fiscal Period Close FY22
The working document was a Google Sheet. This table is here for informational purposes and for future reference.
Task | Task Name | Duration | Start | Finish | Predecessors | Assigned To | Comments |
---|---|---|---|---|---|---|---|
1 | Review all rollover documentation | 7d | 05/10/22 | 05/18/22 |
| All | |
2 | Department review of financial reports, and make adjustments as needed | 16d | 05/10/22 | 05/31/22 |
| Library Finance | Marking complete on June 28th since FY22 is closed |
3 | Review encumbrances for appropriateness, make needed adjustments | 16d | 05/10/22 | 05/31/22 |
| Selectors | Marking complete on June 28th since FY22 is closed |
4 | Review and ensure all expected transfer journals are accounted for are fully approved by month end | 16d | 05/10/22 | 05/31/22 |
| Library Finance | Marking complete on June 28th since FY22 is closed |
5 | Review, substantiate, and submit any purchasing card transactions from all closed statement periods | 19d | 05/10/22 | 06/03/22 |
| Selectors | Marking complete on June 28th since FY22 is closed |
6 | Onboard suppliers for goods or services that are planned to purchase in FY22 | 16d | 05/10/22 | 05/31/22 |
|
| Marking complete on June 28th since FY22 is closed |
7 | Enter Requests for purchases and submit for approval, for FY22 purchase of goods and services | 16d | 05/10/22 | 05/31/22 |
| Selectors/Acquisitions | Marking complete on June 28th since FY22 is closed |
8 | Notify Acquisitions Department to close fully executed or unneeded POs | 16d | 05/10/22 | 05/31/22 |
| Selectors | Marking complete on June 28th since FY22 is closed |
9 | Move active PO lines still attached to Voyager ledger to current fund structure | 10d | 05/19/22 | 06/01/22 |
|
|
|
10 | Convert one-time orders that are currently Partially Invoiced to Fully Invoiced | 4d | 05/24/22 | 05/27/22 |
|
|
|
11 | Perform receipt of goods in Alma when physically received | 16d | 05/10/22 | 05/31/22 |
| Acquisitions/Holdings Management |
|
12 | Rollover test 1: one ledger in sandbox | 0 | 05/19/22 | 05/19/22 |
| Alma Tech Team | Science Ledger |
13 | Rollover test 1: one PO line in sandbox | 1d | 05/19/22 | 05/19/22 | 12 | Alma Tech Team | 22660-princetondb; also try 1046794-princetondb |
14 | Rollover test 1: review results | 1d | 05/20/22 | 05/20/22 | 13 | Alma Tech Team |
|
15 | Rollover test 2: all ledgers in sandbox | 0 | 05/26/22 | 05/26/22 |
| Alma Tech Team | Began at 10:39 AM; took 1 minute; for this year, we should roll over each ledger individually to avoid rolling over the ledger (named 'FY22') with the old fund structure; run in Draft, then Activate after evaluating the balances |
16 | Rollover test 2: all PO lines in sandbox in Report mode | 0 | 05/26/22 | 05/26/22 | 15 | Alma Tech Team | POL Rollover cannot be undone; began at 11:05 AM and ended at 9:16 PM |
17 | Rollover test 2: review results | 1d | 05/26/22 | 05/26/22 | 16 | Alma Tech/Acq/Finance | 199 lines did not roll over due to being on old Voyager funds; we will work to move them to proper funds in prod prior to the prod rollover |
18 | Rollover test 3: all PO lines in sandbox in Update mode | 0 | 05/27/22 | 05/27/22 |
| Alma Tech Team | Began at 11:31 AM; finished 5/28 at 6:50 AM |
19 | Rollover test 3: review results | 6d | 05/27/22 | 06/03/22 | 18 | Alma Tech/Acq/Finance |
|
20 | All invoices must be received by Library Finance for FY22 by 4:30 PM | 0 | 06/15/22 | 06/15/22 |
|
|
|
21 | Last day to import EDI invoices by 4:30 PM | 0 | 06/15/22 | 06/15/22 |
|
|
|
22 | Disable EDI loading on vendors that are on auto-pilot (EBSCO and Midwest) | 1d | 06/16/22 | 06/16/22 |
|
|
|
23 | Last day to approve invoices in ALMA by 4:30 PM | 0 | 06/16/22 | 06/16/22 |
|
| Final export of invoices from Alma is 6/16 at 7 PM |
24 | Disable voucher feed lib-job script | 0 | 06/17/22 | 06/17/22 |
| Alma Tech Team |
|
25 | Delete 'In Review' invoices by 4:30 PM | 0 | 06/21/22 | 06/21/22 |
|
|
|
26 | Convert one-time orders that are currently Partially Invoiced to Fully Invoiced | 0 | 06/21/22 | 06/21/22 |
|
|
|
27 | Disable loaders for PO lines | 8d | 06/22/22 | 07/01/22 |
| Alma Tech Team |
|
28 | Disable PeopleSoft integrations | 6d | 06/24/22 | 07/01/22 |
|
|
|
29 | Disable jobs that touch invoices and PO lines | 8d | 06/22/22 | 07/01/22 |
| Alma Tech Team | PO renewal was not able to be closed, but other jobs were disabled |
30 | All work on invoices stopped | 7d | 06/22/22 | 06/30/22 |
| Finance |
|
31 | All work on PO lines stopped by 4:30 PM | 5d | 06/21/22 | 06/27/22 |
| Acq/Finance | All work on PO lines was stopped by noon June 22 |
32 | Inactivate FY22 Ledgers, Summary, and Allocated Funds | 0 | 06/22/22 | 06/22/22 |
|
|
|
33 | Create report of final FY22 budget | 1d | 06/22/22 | 06/22/22 | 27 |
|
|
34 | Reconcile Alma report of final FY22 numbers with Prime | 1d | 06/22/22 | 06/22/22 |
|
| This review will happen throughout the year, quarterly |
35 | Rollover test 3: all ledgers in production rolled over in draft | 0 | 06/22/22 | 06/22/22 | 34 | Alma Tech Team |
|
36 | Rollover test 3: review ledger rollover and draft budget reports | 1d | 06/22/22 | 06/23/22 | 36 | Alma Tech Team | Allocated Balances for FY23 matched all cash balances from FY22, so the final FY22 report for funds can be used for fund allocation work |
37 | Rollover test 3: roll over all PO lines in Report mode | 1d | 06/22/22 | 06/23/22 | 37 | Alma Tech Team | Started at 2:50 PM on 6/22; ended at 6 PM; first attempt resulted in most lines failing due to the FY23 funds being in Draft; running a second time, began at 9 AM on 6/23 and finished at 2 PM on 6/23 for the one-time orders and went from 6 PM on 6/23 to 12:03 AM on 6/24 |
38 | Rollover test 3: review PO line rollover reports | 1d | 06/23/22 | 06/24/22 | 37 | Alma Tech Team | No lines had errors |
39 | All physical receiving stopped at 5 PM | 5d | 06/24/22 | 06/30/22 |
| Receiving |
|
40 | All activation/deactivation of portfolios attached to PO lines stopped at 5 pm | 5d | 06/24/22 | 06/30/22 |
| Electronic Resources |
|
41 | All work on physical holdings and portfolios attached to orders stopped at 5 PM | 5d | 06/24/22 | 06/30/22 |
| Electronic Resources/Cataloging/Acq |
|
42 | Production rollover: delete all FY23 draft ledgers | 0 | 06/27/22 | 06/27/22 |
| Alma Tech Team |
|
43 | Production rollover: roll over all ledgers in Update mode | 0 | 06/27/22 | 06/27/22 |
| Alma Tech Team | Began at 9:37 AM on 6/27, completed at 9:39 AM |
44 | Production rollover: run initial budget report | 0 | 06/27/22 | 06/27/22 | 42 | Alma Tech Team |
|
45 | Production rollover: roll over all PO lines in Update mode | 1d | 06/27/22 | 06/28/22 | 42 | Alma Tech Team | Began at 9:53 AM on 6/27, completed at 8:55 AM on 6/28; PO lines attached to an In Review PO did not roll over (see PO-799006) |
46 | Production rollover: review PO line rollover reports | 1d | 06/28/22 | 06/28/22 | 44 | Alma Tech Team/Acq/Finance/Selectors | No errors |
47 | Production rollover: create budget report that includes encumbrances | 1d | 06/28/22 | 06/28/22 | 44 |
|
|
48 | Re-enable PeopleSoft integrations and all Acquisitions jobs | 0 | 06/28/22 | 06/28/22 |
|
|
|
49 | Audit fund balances | 3d | 06/28/22 | 06/30/22 | 46 | Alma Tech Team/Acq/Finance | Alma Tech Team looked at the encumbrances left on FY22 and found that lines fully invoiced in FY22 but not yet received have an encumbrance remaining in FY22 until the item is received |
50 | Fund allocation work for FY23 ledger | 13d | 06/28/22 | 07/14/22 | 46 |
|
|
51 | FY23 open for activity except for invoice approval | 0 | 07/01/22 | 07/01/22 |
|
|
|
52 | First day invoices can be approved for FY23 | 0 | 07/07/22 | 07/07/22 |
|
|
|
53 | Turn in budget reports to Patty by 4:30 PM | 0 | 07/08/22 | 07/08/22 |
| Selectors | Next year, this will be the middle of May |
54 | FY 23 Endowment income distributions and general endowment allocations post | 0 | 07/21/22 | 07/21/22 |
|
|
|