06/28/2021 -Go-Live Project Status
Alma migration
06/28/2021
Current health: On Track
Project status:
The first phase of the Voyager cutover started as planned and is on track. The acquisition and cataloging activities have stopped in Voyager as part of the freeze.. The team also successfully ran the fiscal close this week. The process for Voyager data extraction started on 06/24 evening and will continue into next week.
Key Milestones & Deliverables status
Milestones | Date | Status |
Acquisitions activities stops | 06/21/21 | GREEN |
Perform fiscal period close | 06/22/21 | GREEN |
Cataloging activities stops | 06/24/21 | GREEN |
ReCAP accession stops | 06/24/21 | GREEN |
Voyager data extraction process started | 06/24/21 | IN-PROGRESS |
Alma Configuration Freeze | 07/02/21 | Not started |
SFX Freeze | 07/02/21 | Not started |
Link to the project cutover plan: https://app.smartsheet.com/b/publish?EQBCT=52f14ae2f8754cc791a4231cce18fea8