06/28/2021 -Go-Live Project Status

Alma migration

06/28/2021

 

Current health: On Track

 

Project status:

The first phase of the Voyager cutover started as planned and is on track. The acquisition and cataloging activities have stopped in Voyager as part of the freeze.. The team also successfully ran the fiscal close this week. The process for Voyager data extraction started on 06/24 evening and will continue into next week.

Key Milestones & Deliverables status

Milestones

Date

Status

Acquisitions activities stops

06/21/21

GREEN

Perform fiscal period close

06/22/21

GREEN

Cataloging activities stops

06/24/21

GREEN

ReCAP accession stops

06/24/21

GREEN

Voyager data extraction process started

06/24/21

IN-PROGRESS

Alma Configuration Freeze

07/02/21

Not started

SFX Freeze

07/02/21

Not started

 

Link to the project cutover plan:          https://app.smartsheet.com/b/publish?EQBCT=52f14ae2f8754cc791a4231cce18fea8