Current health: On Track
Project status:
We are on track with the activities planned for the pre-go-live period. The Voyager data extraction was completed successfully this week. The teams started training on 6/28 and are on schedule. The Alma configuration will freeze by the end of the day today. SFX extract will begin on 07/07.
Key Milestones & Deliverables status
Milestones | Date | Status |
Acquisitions activities stops | 06/21/21 | GREEN |
Perform fiscal period close | 06/22/21 | GREEN |
Cataloging activities stops | 06/24/21 | GREEN |
ReCAP accession stops | 06/24/21 | GREEN |
Voyager data extraction is complete | 06/24/21 | GREEN |
Alma training started | 06/28/21 | IN-PROGRESS |
Alma Configuration freeze (EOD) | 07/02/21 | GREEN |
SFX freeze (EOD) | 07/02/21 | GREEN |
SFX extract | 07/06/21 | Not started |
Important links:
project cutover plan: https://app.smartsheet.com/b/publish?EQBCT=52f14ae2f8754cc791a4231cce18fea8
Training schedule:Training Schedule - Alma - Princeton University Library Confluence