07/02/2021 -Go-Live Project Status

Alma migration

07/02/2021


Current health: On Track

Project status: 

We are on track with the activities planned for the pre-go-live period. The Voyager data extraction was completed successfully this week. The teams started training on 6/28 and are on schedule. The Alma configuration will freeze by the end of the day today. SFX extract will begin on 07/07.

Key Milestones & Deliverables status

Milestones

Date

Status

Acquisitions activities stops

06/21/21

GREEN

Perform fiscal period close

06/22/21

GREEN

Cataloging activities stops

06/24/21

GREEN

ReCAP accession stops

06/24/21

GREEN

Voyager data extraction is complete

06/24/21

GREEN

Alma training started

06/28/21

IN-PROGRESS

Alma Configuration freeze (EOD)

07/02/21

GREEN

SFX freeze (EOD)

07/02/21

GREEN

SFX extract

07/06/21

Not started

Important links:

project cutover plan: https://app.smartsheet.com/b/publish?EQBCT=52f14ae2f8754cc791a4231cce18fea8

Training schedule:Training Schedule - Alma - Princeton University Library Confluence